2,500-Ton Rail Bridge Jacked into Place at Tampere Station
Crews jacked a 2,500-ton railway bridge into place at Tampere station in early November as part of the Transport Infrastructure Agency's rail yard project.
According to the City of Tampere, in early November crews jacked a 2,500-ton railway bridge into place at Tampere railway station, part of the Transport Infrastructure Agency's Tampere rail yard project. The move follows earlier work on the scheme, including the first bridge deck pour in late September and earthworks begun earlier this year for a third station platform.
The bridge is 60.5 metres long and 13 metres wide. It contains roughly 170 tonnes of steel and 950 cubic metres of concrete. Jetro Matilainen, project manager for the Transport Infrastructure Agency, said the tight site forced a vertical jacking solution because there was no room for the usual sideways slide-in. Trams were able to keep running under the works without interruption. Kreata foreman Jere Vesanen said crews lifted the span five centimetres a few weeks earlier to remove wooden formwork. The actual lowering operation took seven hours.
The operation was planned during the bridge's construction, with extra reinforcement. Crews executed the move from eight jacking points, using two towers, and 250 mm shims were removed alternately as the load transferred. The span is the third of six bridges in the scheme. The Ratapihankatu and Erkkilä bridges are already finished. Larger works around the station, including deck surfacing and track installation, will continue in spring, and the first rail bridge is due to open for rail traffic next spring when the third intermediate platform is completed.
Earlier coverage
Catch the full story over at City of Tampere
Image Attribution
Artist: Robert Dezso / Tampere Today
License: Own work